We have completed all of the voice and data cable pulls (464). We placed (122) 2410 telephones, programmed (480) ports, 6-coverage paths, and 14-intercom groups.
We turned up and tested (8) T1s at the CBS compound, and (2) T1s at the “Production Hotel.”
The day was not without adventure. The (30) cables we were to pull at the South Beach location for the CBS Early show, were delayed because local authorities felt we did not have the proper permit to run cables over a “public access” road. Needless to say, we did not get much work done, so we are now one full day behind schedule for South Beach. One last thing, in my haste to reach the site, I forgot my camera at the CBS Compound, so no pictures of the 5-foot waves, and the surfers.